We use cookies to collect information about how you use our website. We use this data to make the site work well and improve our services.

Greenbrow Social Club

Wythenshawe Community Housing Group (WCHG)

Case study
Scroll Down

Project Overview

This scheme was directly awarded to Casey by WCHG, following the success of the Benchill Road new build scheme.

Programme & Construction Technique

Casey has successfully delivered the development of 8 affordable houses and 15 apartments of traditional build on the site of the former Greenbrow Social Club in Wythenshawe. Prior to build commencement, we demolished the former social club, removed any asbestos contamination and filled the associated basement void with engineered soil, before installing a capping layer and gas membrane.

Additionally, ASHPs, MVHRs and EV charging points were installed in each/for every unit, alongside the construction of a designated cycle store, communal car park and soft landscaping.

Challenges Overcome

The works was surrounded by a housing estate, so resident engagement was crucial. Our Stakeholder Engagement Manager and Site Manager frequently met with residents to update them on the programme of works, notify them of delivery schedules and discuss any concerns in an open forum. At the commencement of the project, existing resident parking was tricky to navigate, however once we came to an agreed arrangement, access/egress was no longer an issue.

Successful Outcome

“The Greenbrow scheme has been a fantastic success. Casey delivered the project with real care for our residents and the surrounding community. The site was really well managed, there were no complaints form the residents. The quality of the new homes is outstanding, communication was excellent throughout.”

James Garner, WCHG

Social Value

During this scheme, we delivered £345,000 of Social Value, including 68 apprenticeship weeks, job creation for 1 full-time employee and over £140,000 in local supply chain spend and donations.

We were able to further our connections with the local communities by giving back to local primary school, Ashgate Primary. In collaboration with WCHG, we supported them after discovering their car park was unsafe and they could not meet the full cost of repairs.

Through our Improving Lives Fund, we contributed over £10,000 to complete the resurfacing, directly improving accessibility and safety for pupils, staff and families. We also donated Easter Eggs and contributed to their summer missions. Furthermore, we donated resources, time and money to local charities, including Safespots and Be a Part of Change.

Additionally, we donated a defibrillator to Safespots. Debbie, who runs the centre, expressed her deep gratitude to Casey for our donation:

“Thank you ever so much for considering us. Everyone at the centre is extremely grateful for your kind donation.”

click to enlarge

Building Relationships

As we have a strong working relationship through successful delivery of many previous schemes, the client team are familiar with Casey and are well versed in our working practices. This scheme was directly awarded to Casey following the success of the Benchill new build housing scheme completed for WCHG.

Social values

We were able to further our connections with the local communities by giving back to local primary school, Ashgate Primary. In collaboration with WCHG, we supported them after discovering their car park was unsafe and they could not meet the full cost of repairs.

Through our Improving Lives Fund, we contributed over £10,000 to complete the resurfacing, directly improving accessibility and safety for pupils, staff and families. We also donated Easter Eggs and contributed to their summer missions. Furthermore, we donated resources, time and money to local charities, including Safespots and Be a Part of Change.

Go back to case studies